Name: |
Tramore Golf Club |
Website: | www.tramoregolfclub.com |
Contract Type: |
Traditional IEI Contract |
Client: |
Tramore Golf Club |
Company Involvement: |
Tramore Golf Club awarded EGS the contract in 2007. EGS were the main contractors for the project. Jeff Howes Design were the Architects for the project.
Start / End Date: |
April 2007 – October 2009 |
|
|
Project Description: |
The contract comprised of the following: |
|
The project was in three stages. Remodelling of the original 18 holes and construction of a new short game area and Putting green on the existing site, and the construction of a new 9 holes Installation of Irrigation to the new green and adapting the system to new green locations. Other works include diverting the stream through the site in 3 location and the installation of rock armour and bridge crossings, the reconstruction of 6 Tee complexes and general mounding throughout the site.