Drainage project - New Forest Golf Resort, Tyrellspass, Ireland
Partial drainage system of fairways connecting in to the existing main drain pipe work adding additional laterals as necessary. Slit drainage installed at 1 to 1.5 metre spacing
Name: |
New Forest Golf Resort, Tyrellspass, Ireland |
Website: | |
Contract Type: |
Traditional IEI contract |
Client: | Eassda Group |
Company Involvement: |
Eassda Group awarded the contract to EGS in 2005. EGS were the main contractors for the project. Peter McEvoy, Sporting Concepts, were the Architects and ? were the Engineers for the roads and infrastructure.
Start / End Dates: |
February 2005 – March 2006 |
Project Description: | The contract comprised the following: |
|
The development consisted of an 18 hole golf course, driving range, housing development and hotel site, covering approximately 60 hectares.